Cooling Question 7
We are having to stop our kiln at frequent intervals because of ring build-ups. When we raise the alumina modulus to ...
Re: Cooling
Ring formation is caused by the formation of liquids in the kiln at a particular position. These penetrate the refrac...
Cooling Question 8
Hot clinker is quenched in water losing useful heat, can you syggest heat recovery without altering process of quench...
Re: Cooling
The white cement clinker must be quenched as it falls from the kiln to freeze the clinker minerals in their high temp...
Cooling Question 9
I want to know about calculation methods of gas and material flow in preheater, pc, kiln, cooler. Further, can you ad...
Re: Cooling
The calculation of gas and material flow in the preheater relies on the principles of stoichoimetry (to assess the co...
Cooling Question 10
I would like information on the formation of “snowmen” in our kiln cooler. Our kiln produces 2000tpd clinker. The kil...
Re: Cooling
Snowman formation is caused by some of the flux in the clinker remaining as a liquid after the clinker falls into the...
Cooling Question 11
What is the effect of cooler dust on flame?
Cement separators Question 1
My Company is planning to install a New Cement Grinding Plant with a capacity of 150tph, The Supplier is insisting to...