Hello every one ...

Today i want to discuss one decision  about the kiln and i wants your comments ....

 

 We had shut down for Kiln maintenance  and for Raw mill ....(rooler liner and table liner and rotary feeder liner changing are the major jobs in MPS Pfiffer 350tph)


we had completed our kiln jobs before the raw mill maintenance

before the shutdown we had about 6000tons raw meal in the silo.......... 

when we start the kiln firing .....that time  mill had at least three days jobs but our seniors decide to preheat the kiln for 24hr and also start the kiln feed....and unfortunately silo became empty at that spot mechanical team declare that, they had still three two day job ....

so or senires decide to keep  the flame on to maintain the Inlet temperature about 800C...so  we consumed 1.5tph coal along 350lit/hr diesel .........and that falme continue for the three days ...........

My idea was that ...let stop the firing till mechanical clearance for the mill and start the firing after at least four hour production of raw meal...........

What You people say about this story ..............