C3A

To what degree is setting time retarded when C3A is only 8% or almost 7% and or vice versa 12%?

Reply


Know the answer to this question? Join the community and register for a free guest account to post a reply.

yadavd
31 posts
TimePosted 16/09/2011 11:41:52
yadavd says

Re: C3A

if C3A is higher than reaction of Ettringite formation will faster it will set quickly. dilip yadav

Reply

norew
99 posts
TimePosted 18/09/2011 00:56:41
norew says

Re: C3A

For OPC the requirement for C3A is 10%, please compare the setting time if the C3A content of cement is as given above. Thanks

 

Reply

yadavd
31 posts
TimePosted 19/09/2011 11:00:24
yadavd says

Re: C3A

Dear Friend Neorw In our OPC C3A~ 8.0 so setting time is ~135 (initial) and ~ 185 (final) while in case of PPC C3A is ~ 5.5 ( calculated by %CLN in PPC * %C3A in CLN) so setting time is 170 and 220 ( final)

 

So reducing C3A from 8.0 to 5.5 ~ 2.5 % 

 

increase setting time by 25-35 minute 

 

same correlation can be made for your cement ,please send me complete analysis of clinker and cement at my mail

yadavd@shreecementltd.com

i will further explain on basis of your results

 

with regards

dilip yadav