10 posts
TimePosted
13/02/2012 03:42:01
elminia
says
drying and heating up program
Dear All,
Please tell me how long time is recommended for drying and heating up for a kiln 3.15 x 47 m ,
after 2 years stoppage time and new SPINEL Bricks in Burning zone.
The place of this kiln is in one tropical country,with very High moisture content and very high temperature, with a big diference between day and night temperature.
Rebricking of burning zone was made 3 months ago.
Many thanks.
Kind Regards,
Know the answer to this question? Join the community and register for a free guest account to post a reply.
55 posts
10 posts
81 posts
TimePosted
18/02/2012 09:26:06
fjalali
says
re drying and heating up program
Can i have the article as well please.
Thx