Dangote Cement’s new cement factory in Douala, Cameroon, is on-track to start producing its first cement in May 2014, the plant’s general manager has said.
“The installation activities are ongoing. Engineering is almost 100 per cent done, procurement about 90 per cent, construction we have attained about 60 per cent and we hope that by April or May 2014, we should be in the market,” Adullali Baba told local press.