Geseke CCS project reaches technical planning phase12 November 2024, Published under Cement NewsIn October, with the awarding of the contract, for GeZero between Heidelberg Materials and Fluor Corp the GeZero Carbon capture and storage (CCS) project at Geseke cement plant enters a crucial technical planning phase. The technical planning is expected to be completed by next spring, with construction set to begin in 2026. The front-end engineering design (FEED) represents the detailed technical planning for the GeZero decarbonisation project, the first large-scale CO 2 capture and s... |