Gebr Pfeiffer has won a contract to supply two vertical roller mills for Semen Bosowa’s Line No 2, which is being constructed at the Indonesian producer's cement works located near Maros, Sulawesi.
Sinoma International Engineering Co Ltd, acting as General Contractor for the new 5500tpd cement production line, awarded Gebr Pfeiffer the contract for an MPS 5600 B for raw material grinding and an MPS 3750 BK for coal grinding.
The MPS raw mill sold is designed for a capacity of 480tph and the MPS coal mill for 60tph .
Apart from the supply of the key components for the grinding plants, the order includes the supply of workshop drawings to enable the local manufacture of mill components and the supervision of manufacture at Chinese workshops. Moreover, erection and commissioning on site will be supervised by staff from Gebr Pfeiffer.
Delivery is scheduled for the first quarter of 2014.
Crown Cement earned a profit after tax of BDT1001m in FY24
Crown Cement PLC, in Bangladesh, recently released its annual report for FY23-24. During the las...