Tianjin Cement Industry Design & Research Institute Co Ltd has ordered two LM 53.3+3 CS Loesche clinker grinding mills for PT Semen Baturaja in Indonesia.
Both of the mills have a capacity of 175tph with material ground to a fineness of 3400 Blaine. Each mill is fitted with a gearbox with a power of 4200kW.
The leadtime for the main components of the mill is nine months and the gearboxes are supplied within 12 months. The commissioning of both vertical roller mills is planned for the end of next year.
The order follows a previous delivery in 2012 of the LM 46.2+2 CS Loesche mill, which is still in operation.
In 2013 Loesche GmbH established the subsidiary company PT Loesche Indonesia with an office in the capital Jakarta.