Katavsky Cement JSC, part of the Eurocement Group, produced 128,255t of cement, 10,255t than the planned figure.

Between January to August, 656,625t of high-quality product was manufactured.

The plant also produced 73,068 tons of clinker which is 12.4% above target. During the first eight months of this year 478,663t of clinker were produced. Compared with 2010 this figure had risen by 9.4%.

Katavsky Cement shipped 143,690t of finished products to its consumers in August, thus exceeding its target by 2.6%.